BAO Administration's Impactful Projects Transforming Ekiti's Infrastructure

Under the visionary leadership of the BAO Administration, the Ministry of Works in Ado Ekiti is spearheading numerous projects aimed at enhancing the state's infrastructure. These projects, carried out by various local contractors, are making significant strides in improving connectivity and overall development across Ekiti.

Here's a detailed look at the projects contributing to this transformative impact:

1. Additional works on the rehabilitation of selected roads in Ado and Ikere Ekiti
   - Contractor: Dortmund and Company Ltd
   - LGA of Location: Ado LGA
   - % of Completion: 98%

2. Rehabilitation of Igarabdo-Ikogosi Road
   - Contractor: Dortmund and Company Ltd
   - LGAs of Location: Ekiti South West & Ekiti West
   - % of Completion: 88.69%

3. Rehabilitation of Ilawe-Igede Road
   - Contractor: Leadgate Nig, Ltd
   - LGAs of Location: Ekiti South West & Irepo/Ife/Ilo/Lodun
   - % of Completion: 78.00%

4. Rehabilitation of Ilawe-Erijinyan Road
   - Contractor: Leadgate Nig, Ltd
   - LGAs of Location: Ekiti South West & Ekiti West
   - % of Completion: 97.14%

5. Rehabilitation of Hospital Management Board Road, Ado-Ekiti
   - Contractor: Dortmund and Company Ltd
   - LGA of Location: Ado LGA
   - % of Completion: 54%

6. Construction of Ikole-Ara-Isinbode Road
   - Contractor: Dromo Int'l Nig Ltd
   - LGAs of Location: Ikole & Gbonyin
   - % of Completion: 13.60%

7. Rehabilitation of Ado-Ilawe Road
   - Contractor: Dromo Int'l Nig Ltd
   - LGAs of Location: Ado & Ekiti South West
   - % of Completion: 86.47%

8. Construction of Phase II (Dual Carriageway between GRA III Extension and Pavilion-NTA Road) Ado-Ekiti
   - Contractor: Rudy Construction Nigeria Ltd
   - LGA of Location: Ado LGA
   - % of Completion: 16.50%

9. Reconstruction of Ikere-Igarabdo Odo Road
   - Contractor: Step Development Limited
   - LGAs of Location: Ikere & Ekiti South West
   - % of Completion: 2.83%

10. Construction of Ekiti Ring Road - Phase 1
    - Contractor: Craneburg Construction Company Ltd
    - LGAs of Location: Irepo/Ifelodun & Ado
    - % of Completion: 1.96%

11. Construction of Flyover Bridge from Ajilosun (Union Bank) to Okeyinmi (First Bank), Ado-Ekiti
    - Contractor: Step Development Limited
    - LGA of Location: Ado LGA

12. Rehabilitation of Ikere-Ise-Emure Ekiti Road
    - Contractor: Dromo Int'l Nig Ltd
    - LGAs of Location: Ikere, Ise/Orun & Emure
    - % of Completion: 5.21%

13. Construction of Obisesan Road, Oke-Ala Basiri, Ado-Ekiti
    - Contractor: Wals and Funs Nigeria Ltd
    - LGA of Location: Ado LGA
    - % of Completion: 27.29%

14. Reconstruction of Iloro-Ijurin-Temidire-Ayegunle Ekiti Road and additional works on completion of construction of Oke-Ero-Ilukuno-Ipoti Ekiti Road
    - Contractor: Roosco Resources Nigeria Ltd
    - LGA of Location: Ijero LGA
    - % of Completion: 15.00%

15. Rehabilitation of Itapa-Ijelu-Omu Road and additional works on construction of River Ele Bridge, Itapa
    - Contractor: Delko Holdings Nigeria Ltd
    - LGA of Location: Oye LGA
    - % of Completion: 14.40%

16. Reconstruction of Ikere-Ilawe Ekiti Road
    - Contractor: Peculiar Ultimate Concerns Ltd
    - LGAs of Location: Ikere & Ekiti South West
    - % of Completion: 14.29%

17. Review of the contract award for the rehabilitation of Agric Olope-Moferere-Agric Olope-Odo-Ado Road
    - Contractor: Kouris Construction Nigeria Ltd
    - LGA of Location: Ado LGA
    - % of Completion: 95.18%

18. Review of the contract award for the construction of GRA III Extension Road, behind NTA Ado-Ekiti
    - Contractor: Rudy Construction Nigeria Ltd
    - LGA of Location: Ado LGA
    - % of Completion: 39.95%

19. Reconstruction of Atlas - (Ajebandele) Deeper Life-Alasia-Shepherd-Omisanjana Road, Ado-Ekiti
    - Contractor: CCECC Nigeria Ltd
    - LGA of Location: Ado LGA
    - % of Completion: 100%

20. Review of the contract award for the construction of Airfield Pavement in Ekiti State Airport, Ado-Ekiti
    - Contractor: CCECC Nigeria Ltd
    - LGA of Location: Ado LGA
    - % of Completion: 65%
    - Note: This project is now being handled by the Ministry of Transport

21. Rehabilitation of Ikole Township Road
    - Contractor: Dromo Int'l Company Ltd
    - LGA of Location: Ikole LGA
    - % of Completion: 77.05%

22. Contract for the additional works on the rehabilitation of Ado-Iworoko-Ifaki Road
    - Contractor: Immobiliare Construction Limited
    - LGAs of Location: Ado, Ire/Ife & Ido/Osi
    - % of Completion: 59.15%

These transformative initiatives are not only improving the physical landscape but also paving the way for a more prosperous and connected Ekiti state.

Comments

Popular posts from this blog

Exposed! Isaac Fayose's Critique of Ekiti Government Fueled by Personal Vendetta, Failed Patronage Bid

Oyebanji Has Done Well: Kayode Ojo Commends Ekiti Airport

‘The BAO Walk’ Initiative Gains Momentum